SYSTEMS STATUS

Georgia Power Scheduled Maintenance - Barrow County Schools (KBAR)

Scheduled Maintenance Report for USG Services

Completed

The scheduled maintenance has been completed.
Posted Jul 17, 2026 - 23:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 17, 2026 - 18:00 EDT

Scheduled

Georgia Power will be cutting power to the data center building.

This maintenance will occur on Friday, July 17, 2026 at 6:00 p.m. until 11:00 p.m.

It has the potential to take our optical and routing equipment down for KBAR. We anticipate that the UPS will hold until a generator kicks in.
Posted Jul 13, 2026 - 14:43 EDT
This scheduled maintenance affected: PeachNet Network (USO Athens Office).