SYSTEMS STATUS
PeachNet Maintenance at Abraham Baldwin Agricultural College (ABAC)
Scheduled Maintenance Report for USG Services
Completed
The scheduled maintenance has been completed.
Posted Jul 06, 2017 - 07:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 05, 2017 - 23:00 EDT
Scheduled
Communications Consulting Group (CCG) will be replacing UPS batteries, performing tests on the UPS, and reconfiguring some cables for power diversity at Abraham Baldwin Agricultural College (ABAC) from 11:00 p.m. on Wednesday, July 5, 2017 until approximately 7:00 a.m. on Thursday, July 6, 2017 (ET). During this period, devices other than the modem and terminal server will run on their redundant power supply. No outages are expected.
Posted Jun 29, 2017 - 11:05 EDT
This scheduled maintenance affected: PeachNet Network (Abraham Baldwin Agricultural College).