SYSTEMS STATUS
PeachNet Network Scheduled DWDM Maintenance - North Ring
Scheduled Maintenance Report for USG Services
Completed
The scheduled maintenance has been completed.
Posted Feb 19, 2021 - 05:00 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 18, 2021 - 23:01 EST
Scheduled
Network Support Services (NSS) & Communications Consulting Group (CCG) will be working to complete the North Ring installation of DWDM and switching components.

GSU locations on that ring Georgia State University - Alpharetta (GSUALP), Georgia Perimeter College - Alpharetta (GPCALP) and Georgia State University - Dunwoody Campus (GPCDUN) will experience outages.

This maintenance will occur Thursday, February 18, 2021 at 11:00 p.m. until Friday, February 19, 2021 at 5:00 a.m.

Services affected: Services to GSUALP/GPCALP and GPCDUN
Posted Feb 02, 2021 - 10:20 EST
This scheduled maintenance affected: PeachNet Network (Georgia State University).