SYSTEMS STATUS
DWDM Firmware Upgrade Maintenance
Scheduled Maintenance Report for USG Services
Completed
The scheduled maintenance has been completed.
Posted Dec 18, 2018 - 03:01 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 17, 2018 - 23:00 EST
Scheduled
Communications Consulting Group (CCG) and Network Support Services (NSS) will be performing firmware upgrades on DWDM 10TCC cards on Monday, December 17, 2018 from 11:00 p.m. until Tuesday, December 18, 2018 at 3:00 a.m. PN0191A/B and PN0129A/B/C are the only non-redundant services on the scheduled cards and therefore will experience an outage lasting approximately 30 minutes.

Services affected:
PN0191A/B from TELX to Georgia Southern University - Armstrong Campus for Apogee
PN0129A/B/C from TELX to South Georgia State College - Waycross Campus for Alma Telephone Company
Posted Dec 13, 2018 - 15:07 EST
This scheduled maintenance affected: PeachNet Network (USO Athens Office).